Jekyll Island Beachfront Shoreline Rock Revetment Rehabilitation Project

Phase 2

In general, Phase 2 of the project (including bid alternatives) consists of utilizing an approved upland borrow source for fill placement of about 120,000 cubic yards of beach compatible material along nearly 15,000 linear feet of shoreline (landward of an existing rock revetment and along a small active beach area);  placement of geotextile materials; construction of a ~230 linear feet armor stone revetment; installation of a ~150 linear feet geotextile tube; beach and dune plantings; and installation of sand fencing and dune rope fencing.

Jekyll Island Phase 2 Bid Documents (PDF)

Jekyll Island Shoreline Rehabilitation Bid Drawings


Phase 1

The apparent lowest bidder responsive to RFP 351 is S.J. Hamill Construction Company, LLC. The JIA is moving forward with due diligence and final contract negotiation with S.J. Hamill. Thank you for your interest in this RFP.

Jekyll Island Revetment Rehabilitation Contractor Bids (PDF)

Project Update June 19, 2018: ATM Rock Revetment Rehabilitation


Project updates from S. J. Hammill Construction Company will be provided weekly. Should you have any additional questions for the team on this project, please direct them to:

Marty Kenealy, Project Manager | S.J. Hammill, Construction Company, LLC
Phone: 843.872.8002 | Email: marty@sjhamill.com


STA represents stationing along the beach. Please refer to map for specific stationing locations.

November 19-23, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+50 to 14+50 THROUGHOUT THE WEEK

Monday (11/19)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 17+50)
  • Construction of revetment to be from STA 19+00 to 17+50

Tuesday (11/20)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 16+00)
  • Construction of revetment to be from STA 17+50 to 16+00

Wednesday (11/21)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 14+50)
  • Construction of revetment to be from STA 16+00 to 14+50

Thursday (11/22) (Thanksgiving)

  • OFF – no construction activities

Friday (11/23)

  • OFF – no construction activities

November 10-16, 2018

Saturday (11/10)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview Drive.

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+50 to 67+00 THROUGHOUT THE WEEK

Monday (11/12) (Veteran’s Day Observed)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 26+25)
  • Construction of revetment to be from STA 27+50 to 26+25

Tuesday (11/13)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 25+00)
  • Construction of revetment to be from STA 26+25 to 25+00

Wednesday (11/14)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 23+75)
  • Construction of revetment to be from STA 25+00 to 23+75

Thursday (11/15)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 22+50)
  • Construction of revetment to be from STA 23+75 to 22+50

Friday (11/16)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 21+25)
  • Construction of revetment to be from STA 22+50 to 21+25

November 3-9, 2018

Saturday (11/3)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview Drive.
  • Construction of revetment to be from STA 73+00 to 72+00

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+50 to 67+00 THROUGHOUT THE WEEK

Monday (11/5)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 71+00)
  • Construction of revetment to be from STA 72+00 to 71+00

Tuesday (11/6)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 70+00)
  • Construction of revetment to be from STA 71+00 to 70+00

Wednesday (11/7)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 69+00)
  • Construction of revetment to be from STA 70+00 to 69+00

Thursday (11/8)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 68+00)
  • Construction of revetment to be from STA 69+00 to 68+00

Friday (11/9)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 67+00)
  • Construction of revetment to be from STA 68+00 to 67+00

October 27-November 2, 2018

Saturday (10/27)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview Drive.
  • Construction of revetment to be from STA 28+00 to 27+00

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+50 to 22+00 THROUGHOUT THE WEEK

Monday (10/29)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) and Access Road #2 (STA 75+50) to Revetment Construction (STA 26+00)
  • Construction of revetment to be from STA 27+00 to 26+00

Tuesday (10/30)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) and Access Road #2 (STA 75+50) to Revetment Construction (STA 25+00)
  • Construction of revetment to be from STA 26+00 to 25+00

Wednesday (10/31)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) and Access Road #2 (STA 75+50) to Revetment Construction (STA 24+00)
  • Construction of revetment to be from STA 25+00 to 24+00

Thursday (11/1)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) and Access Road #2 (STA 75+50) to Revetment Construction (STA 23+00)
  • Construction of revetment to be from STA 24+00 to 23+00

Friday (11/2)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) and Access Road #2 (STA 75+50) to Revetment Construction (STA 22+00)
  • Construction of revetment to be from STA 23+00 to 22+00

October 22-26, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 34+00 to 28+00 THROUGHOUT THE WEEK

Monday (10/22)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 34+00)
  • Construction of revetment to be from STA 34+00 to 33+00

Tuesday (10/23)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 33+00)
  • Construction of revetment to be from STA 33+00 to 32+00

Wednesday (10/24)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 32+00)
  • Construction of revetment to be from STA 32+00 to 31+00

Thursday (10/25)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 31+00)
  • Construction of revetment to be from STA 31+00 to 30+00

Friday (10/26)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 30+00)
  • Construction of revetment to be from STA 30+00 to 29+00

October 13-19, 2018

Saturday (10/13)

  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 38+50)
  • Construction of revetment to be from STA 38+50 to 38+00

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 38+50 to 28+00 THROUGHOUT THE WEEK

Monday (10/15)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 38+00)
  • Construction of revetment to be from STA 38+00 to 37+50

Tuesday (10/16)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 37+50)
  • Construction of revetment to be from STA 37+50 to 37+00

Wednesday (10/17)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 37+00)
  • Construction of revetment to be from STA 37+00 to 36+50

Thursday (10/18)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 36+50)
  • Construction of revetment to be from STA 36+50 to 36+00

Friday (10/19)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 36+00)
  • Construction of revetment to be from STA 36+00 to 35+50

Week of October 1-5, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 44+00 to 28+00 THROUGHOUT THE WEEK

Monday (10/1)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 44+00)
  • Construction of revetment to be from STA 44+00 to 43+00

Tuesday (10/2)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 43+00)
  • Construction of revetment to be from STA 43+00 to 42+00

Wednesday (10/3)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 42+00)
  • Construction of revetment to be from STA 42+00 to 41+00

Thursday (10/4)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 41+00)
  • Construction of revetment to be from STA 41+00 to 40+00

Friday (10/5)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 40+00)
  • Construction of revetment to be from STA 40+00 to 39+00

Week of September 24-29, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 44+00 to 28+00 THROUGHOUT THE WEEK

Monday (9/24)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 44+00)
  • Construction of revetment to be from STA 44+00 to 43+00

Tuesday (9/25)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 43+00)
  • Construction of revetment to be from STA 43+00 to 42+00

Wednesday (9/26)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 42+00)
  • Construction of revetment to be from STA 42+00 to 41+00

Thursday (9/27)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 41+00)
  • Construction of revetment to be from STA 41+00 to 40+00

Friday (9/28)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 40+00)
  • Construction of revetment to be from STA 40+00 to 39+00

Saturday (9/29)

  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 45+00)
  • Construction of revetment to be from STA 45+00 to 44+00

September 22, 2018

Saturday (9/22)

  • On-Road Dump trucks will use N. Riverview Drive, Shell Road, and N. Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 45+00)
  • Construction of revetment to be from STA 45+00 to 44+00

Week of September 10-14, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+50 to 28+00 THROUGHOUT THE WEEK

Monday (9/10)

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 50+00)
  • Construction of revetment to be from STA 50+00 to 49+00

Tuesday (9/11)

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 49+00)
  • Construction of revetment to be from STA 49+00 to 48+00

Wednesday (9/12)

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 48+00)
  • Construction of revetment to be from STA 48+00 to 47+00

Thursday (9/13)

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 47+00)
  • Construction of revetment to be from STA 47+00 to 46+00

Friday (9/14)

  • SHIRMP AND GRITS FESTIVAL – No Work.

Week of September 3-7, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+50 to 28+00 THROUGHOUT THE WEEK

Monday (9/3)

  • LABOR DAY – No Work.

Tuesday (9/4)

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 52+00)
  • Construction of revetment to be from STA 53+00 to 52+00

Wednesday (9/5)

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00)) to Revetment Construction (STA 51+00)
  • Construction of revetment to be from STA 52+00 to 51+00

Thursday (9/6)

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 51+00)
  • Construction of revetment to be from STA 51+00 to 50+00

Friday (9/7)

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 50+00)
  • Construction of revetment to be from STA 50+00 to 49+00

Week of August 27-31, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+50 to 28+00 THROUGHOUT THE WEEK

Monday, August 27

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 53+00)
  • Construction of revetment to be from STA 54+00 to 53+00
  • Walkway access in front of The Cottages (connecting boardwalk to beach side of revetment) to be removed.

Tuesday, August 28

  • on-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 52+00)
  • Construction of revetment to be from STA 53+00 to 52+00
  • Albright Access road improvements

Wednesday, August 29

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 51+00)
  • Construction of revetment to be from STA 52+00 to 51+00
  • Albright Access road improvements
  • Equipment relocation to Albright Access

Thursday, August 30

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 51+00)
  • Construction of revetment to be from STA 51+00 to 50+00

Friday, August 31

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #1 (STA 28+00) to Revetment Construction (STA 50+00)
  • Construction of revetment to be from STA 50+00 to 49+00

Week of August 20-24, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+00 to 58+00 THROUGHOUT THE WEEK

Monday, August 20

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 62+00)
  • Construction of revetment to be from STA 63+00 to 62+00

Tuesday, August 21

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 61+00)
  • Construction of revetment to be from STA 62+00 to 61+00

Wednesday, August 22

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 60+00)
  • Construction of revetment to be from STA 61+00 to 60+00

Thursday, August 23

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 59+00)
  • Construction of revetment to be from STA 60+00 to 59+00

Friday, August 24

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 58+00)
  • Construction of revetment to be from STA 59+00 to 58+00

Week of August 13-17, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+00 to 78+00 THROUGHOUT THE WEEK

Monday, August 13

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 77+00)
  • Construction of revetment to be from STA 77+00 to 76+00

Tuesday, August 14

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 76+00)
  • Construction of revetment to be from STA 76+00 to 75+00

Wednesday, August 15

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 74+00)
  • Construction of revetment to be from STA 75+00 to 74+00

Thursday, August 16

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 64+00)
  • Construction of revetment to be from STA 65+00 to 64+00

Friday, August 17

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 63+00)
  • Construction of revetment to be from STA 64+00 to 63+00

Week of August 6-10, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+00 to 84+00 THROUGHOUT THE WEEK

Monday, August 6

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 83+00)
  • Construction of revetment to be from STA 83+00 to 82+50

Tuesday, August 7

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 82+50)
  • Construction of revetment to be from STA 82+50 to 82+00

Wednesday, August 8

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 82+00)
  • Construction of revetment to be from STA 82+00 to 81+50

Thursday, August 9

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 81+50)
  • Construction of revetment to be from STA 81+50 to 81+00

Friday, August 10

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 81+00)
  • Construction of revetment to be from STA 81+00 to 80+50

Week of July 30-August 3, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+00 to 89+00 THROUGHOUT THE WEEK

Monday, July 30

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 87+00)
  • Construction of revetment to be from STA 87+00 to 86+50

Tuesday, July 31

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 86+50)
  • Construction of revetment to be from STA 86+50 to 86+00

Wednesday, August 1

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 86+00)
  • Construction of revetment to be from STA 86+00 to 85+50

Thursday, August 2

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 85+50)
  • Construction of revetment to be from STA 85+50 to 85+00

Friday, August 3

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 85+00)
  • Construction of revetment to be from STA 85+00 to 84+50

Week of July 23-27, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+00 to 89+00 THROUGHOUT THE WEEK

Monday, July 23

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 89+00)
  • Construction of revetment to be from STA 89+00 to 88+50

Tuesday, July 24

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 88+50)
  • Construction of revetment to be from STA 88+50 to 88+00

Wednesday, July 25

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 88+00)
  • Construction of revetment to be from STA 88+00 to 87+50

Thursday, July 26

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 87+50)
  • Construction of revetment to be from STA 87+50 to 87+00

Friday, July 27

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 87+00)
  • Construction of revetment to be from STA 87+00 to 86+50

Week of July 16-20, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+00 to 97+00 THROUGHOUT THE WEEK

Monday, July 16

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 97+00)
  • Construction of revetment to be from STA 97+00 to 90+70

Tuesday, July 17

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 97+00)
  • Construction of revetment to be from STA 97+00 to 90+30

Wednesday, July 18

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 90+30)
  • Construction of revetment to be from STA 90+30 to 89+80

Thursday, July 19

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 89+80)
  • Construction of revetment to be from STA 89+80 to 89+30

Friday, July 20

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 89+30)
  • Construction of revetment to be from STA 89+30 to 88+80

Week of July 9-13, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+00 to 97+00 THROUGHOUT THE WEEK

Monday, July 9

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 93+50)
  • Construction of revetment to be from STA 93+50 to 93+00

Tuesday, July 10

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 93+00)
  • Construction of revetment to be from STA 93+00 to 92+50

Wednesday, July 11

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 92+50)
  • Construction of revetment to be from STA 92+50 to 92+00

Thursday, July 12

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 92+00)
  • Construction of revetment to be from STA 92+00 to 91+50

Friday, July 13

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 91+50)
  • Construction of revetment to be from STA 91+50 to 91+00

Week of July 2-6, 2018

No work is currently scheduled the week of July 2, but this schedule is subject to change.


Week of June 25-29, 2018

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+00 to 97+00 THROUGHOUT THE WEEK

Monday, June 25

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 96+00)
  • Construction of revetment to be from STA 96+00 to 95+60

Tuesday, June 26

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 95+60)
  • Construction of revetment to be from STA 95+60 to 95+20

Wednesday, June 27

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 95+20)
  • Construction of revetment to be from STA 95+20 to 94+80

Thursday, June 28

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 94+80)
  • Construction of revetment to be from STA 94+80 to 94+40

Friday, June 29

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Jekyll Island Road throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 94+40)
  • Construction of revetment to be from STA 94+40 to 94+00

Week of June 18-22, 2018

 

PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+00 to 97+00 THROUGHOUT THE WEEK

Monday, June 18

  • Commence Armor Stone deliveries with over-the-road trucks to Access Road #2 (STA 75+50)
  • On-Road Dump trucks will use Riverview Drive, Shell Road and Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 97+00)
  • Construction of revetment to be from STA 97+00 to 96+90

Tuesday, June 19

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 96+90)
  • Construction of revetment to be from STA 96+90 to 96+60

Wednesday, June 20

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 96+60)
  • Construction of revetment to be from STA 96+60 to 96+30

Thursday, June 21

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 96+30)
  • Construction of revetment to be from STA 96+30 to 96+00

Friday, June 22

  • On-Road Dump trucks will use Riverview Drive, Shell Road and Beachview Drive throughout the day.
  • Off–Road truck will travel on beach from Access Road #2 (STA 75+50) to Revetment Construction (STA 96+00)
  • Construction of revetment to be from STA 96+00 to 95+80

Week of June 11-15, 2018

Monday, June 11

  • Commence Armor Stone deliveries with over-the-road trucks to Access Road #2 (STA 75+50)
  • Construct Armor Stone revetment (97+00 to 96+50)
  • PUBLIC BEWARE OF HEAVY EQUIPMENT AND OFF ROAD TRUCKS TRAVERSING THE BEACH FROM STA 75+00 to 97+00

Tuesday, June 12

  • Delivery of heavy equipment to Access Road #2 (south of Villas by the Sea)

Wednesday, June 13

  • Reshaping existing revetment adjacent to Villas by the Sea

Thursday, June 14

  • Commencement of stone deliveries to project site. Placement at beach STA 97+00

Week of June 4-8, 2018

Monday, June 4

  • Access Road #2 improvements directly south of Villas by the Sea (STA 75+50)
  • Demolish existing timber walkways adjacent to Villas by the Sea (STA 77+50 and 80+50)

Tuesday, June 5

  • Demolish existing timber walkways adjacent to Villas by the Sea (STA 77+50 and 80+50)
  • Cleanup and re-align existing stone revetment (STA 75+00 to 97+00)
  • Cleanup beach debris (STA 75+00 to 97+00)

Wednesday, June 6

  • Install chain link fence on each side of Access Road #2 directly south of Villas by the Sea (STA 75+50)
  • Cleanup and re-align existing stone revetment (STA 75+00 to 97+00)
  • Cleanup beach debris (STA 75+00 to 97+00)

Thursday, June 7

  • Install chain link fence on each side of Access Road #2 directly south of Villas by the Sea (STA 75+50)
  • Install Archeological Stabilization Fence adjacent to Villas by the Sea (STA 94+25 to 96+50)
  • Cleanup and re-align existing stone revetment (STA 75+00 to 97+00)
  • Mobilization of Heavy Equipment for Revetment Construction

Friday, June 8

  • Mobilization of Heavy Equipment for Revetment Construction (STA 75+50)
  • Cleanup and re-align existing stone revetment (STA 75+00 to 97+00)